Setting up the Schedule

You can set up the schedule with the Schedule dialog box. To open the Schedule dialog box of a panel application, use one of the following methods:
1) In the Project Manager window, double-click the Schedule node ( ) under Setup node of the concerned panel application
2) In the Project Manager window, right-click the Schedule node ( ) under Setup node of the concerned panel application to bring out the pop-up menu and select Properties.
3) In the menu bar, click Panel ->Schedule. Note that the concerned panel application must be the current panel application or you will be working on the current panel application instead of the concerned panel application.

The Schedule dialog box contains the following pages. Some of the pages appear only when they are needed.

■ General
Described in Section 16.2.1.

■ Start Macro / End Macro
Described in Section 15.2.6.

In this section

  1. 16.2.1Schedule - General Settings
  2. 16.2.2Schedule Details Dialog Box
  3. 16.2.3Time Setting Block

Need PM Designer itself?

V4 for current PK, PT, ITV and PM panels, V2 for older models. Free, sent by email.

Source.Section 16.2 of the PM Designer Software User Manual, Edition 2.0, © Cermate Technologies Inc. (www.cermate.com, service@cermate.com). Reproduced online, with the manual's own figures, by TSL Automation Solutions, authorised Cermate distributor, for users of Cermate HMI panels. PM Designer and PanelMaster are trademarks of Cermate Technologies Inc.